In the packet (5)
- Workers' compensation affidavit, signed BBRS Building Permit Application To Construct, Repair, Renovate Or Demolish a One- or Two-Family Dwelling (PDF, marked 'Revised Mar 2011')
- Construction drawings, drawn to scale and dimensioned 780 CMR 51.00 Massachusetts Residential Code (10th ed.), Chapter R1 Scope and Application (unofficial copy)
- Energy code compliance documentation 780 CMR 51.00 Massachusetts Residential Code (10th ed.), Chapter R1 Scope and Application (unofficial copy)
- Permit fee How to Apply for a Building Permit Through ACA (Accela guide)
- Debris disposal facility named Demolition Approval Package (Fillable PDF)
Filed on Accela Citizen Access (Brookline) (1)
- Building permit application, completed, signed and dated Mass.gov: Building permit applications for non-state-owned buildings
Only when it applies (7)
- Owner authorization for the contractor to apply (when Is the work being done by a contractor (not the homeowner): yes) Building & Permits FAQs - Brookline
- Homeowner exemption affidavit (when Is the work being done by a contractor (not the homeowner): no) Homeowners' Exemption Eligibility Affidavit - Sample (DOCX)
- Construction Supervisor License number on the application, current (when Is the work being done by a contractor (not the homeowner): yes) 780 CMR 10th ed. Chapter 110.R5 Licensing of Construction Supervisors (unofficial copy)
- Flood zone and design flood elevation shown (when Is any part of the lot in a FEMA flood hazard zone: yes) 780 CMR 51.00 Massachusetts Residential Code (10th ed.), Chapter R1 Scope and Application (unofficial copy)
- Certificate of liability insurance, current (when Is the work being done by a contractor (not the homeowner): yes) Building & Permits FAQs - Brookline
- Certified plot plan, stamped by a registered land surveyor (when Does the work change the building footprint or add floor area: yes) Building & Permits FAQs - Brookline
- Public works, water or sewer sign-off (when Does the work change the building footprint or add floor area: yes) Building Department Referral - Stormwater Management and/or Land Disturbing Activities